HPC_10_Mike_tiling
Last edition: Wikinfo(changed_ts)? by Wikinfo(changed_by)?
The PI is responsible to closely follow the progress of the action, and especially to contact NEMO project manager if the delay on preview (or review) are longer than the 2 weeks expected.
Summary
Tiling as a solution to cache blocking: implementation proposal
https://forge.ipsl.jussieu.fr/nemo/ticket/2198#ticket
- Build demonstration branch for the ST
- investigate solution for routine with lbclnk in it (advection for example)
- Test SETTE configuration to highlight possible issue with AGRIF, BDY, iceberg, OASIS …
This work
- depends on implementation of an extended halo
- depends on and will influence the implementation of the DO loop macros
- depends on development of XIOS to accept 2D tiles of data
- will be done by Daley Calvert in collaboration with Andrew Coward, Italo Epicoco, Gurvan Madec and Francesca Mele.
Preview
Tests
Review
Last modified 5 years ago
Last modified on 2019-12-18T11:48:42+01:00